6/18/2023 0 Comments Pls cadd competition![]() ![]() The OHTL is a precondition for optimal function of the Balsfjord-Skaidi line, which continues onwards to the north. It is necessary due to an expected increase in consumption and for greater industrial activity in Northern Norway. The transmission line will eliminate a bottleneck in the main grid between Nordland and Troms counties. For the design of the towers and the foundations, EFLA used specialized Excel Macros along with PLS-Cadd/Tower. Steinþór Gíslason Director | Energy Phone: +3 / +3 E-mail: ReykjavíkĮFLA worked with Statnett from the preparation stage, by assisting with the choice of the line route and making geotechnical estimates for foundation design. In the 160 km 420 kV OHTL from Ofoten to Balsfjord, Statnett decided to use standard Statnett steel portal towers and foundations. EFLA designed all the towers and foundations, and assisted with project and site management.